Mid-Term 2MAPPS Development and
Analysis Schedule
| Date | Milestone |
| 2/2/98 | 2MASS v2.0 Subsystem Deliveries |
| 2/3-15/98 | 2MAPPS v2.0 System Integration and End-to-End Testing |
| 2/16-4/15/98 | RTB testing, pipeline performance validation, final parameter tuning and threshold determination. Revise Subsystem Design Specification Documents (SDS). |
| 3/2/98 | 2MASS Science Team Meeting (IPAC). |
| 3/4/98 | First IR Light, Southern 2MASS Facility. |
| 3/6-6/29/98 | 2MASS-South Commissioning Support and Southern Pipeline Check-out. |
| 4/16/98 | 2MASS-North Operational Processing Begins. Long-term QA and analysis begins. |
| 6/1/98 | 2MAPPS Parallel Development Pipeline Established. |
| 6/1/98 | IRSA v2.0 Software Delivery. |
| 6/30/98 | 2MAPPS v2.1 (south-capable) Subsystem Deliveries |
| 7/1-7/14/98 | 2MAPPS v2.1 System Integration and End-to-End Testing |
| 7/1/98 | 2MASS Explanatory Supplement work begins. |
| 7/15/98 | Define 2MASS Sampler Data Release Night |
| 7/15-8/28/98 | Southern RTB testing, pipeline performance validation, final parameter tuning and threshold determination. Revise Subsystem Design Specification Documents (SDS). |
| 7/20-21/98 | 2MASS Science Team Meeting |
| 8/4/98-3/1/99 | Intensive Analysis of First Release Data |
| 8/26/98 | Final Processing of 2MASS Sampler Data |
| 9/7/98 | 2MASS-South Operational Processing Begins. Long-term QA and analysis begins. |
| 9/1/98 | 2MASS Sampler Data Frozen and Access Tools Available |
| 9/23/98 | Supporting Web Documentation for 2MASS Sampler Release Complete |
| 10/1/982 | Last Processing Date for Inclusion in First Incremental 2MASS Data Release. |
| 10/7/98 | 2MASS "Sampler" Small Data Release. Web DB and Archive Interface available to public for 1 night's data. |
| 11/1/98 | Final Product Generator Definitions |
| 11/1/98-2/28/99 | Develop Catalog Generation Tools. Interim final product generation tests. |
| 3/1/99 | Final Product Generation for First Incremental Data Release |
| 3/1-4/1/99 | Generate Final Figures for Mini-Explanatory Supplement |
| 4/1/99 | UMASS Approval of Data Release. |
| 4/15/99 | First 2MASS Incremental Data Release. |
2/2/98 2MAPPS v2.0 Subsystem Deliveries
Acceptance criteria for 2MAPPS v2.0 include:
Start date and duration dependent on first light from
CTIO and whether northern pipeline will require further modification to
adapt to instrumental changes. Best case estimate of time requirement
is ~2.5 months after first light.
3/16/98 2MASS-North Operational Processing Begins. Long-term QA and analysis begins.
Dependent on conclusions of 3/2/98 Science Team meeting. If there are no additional liens on pipeline resulting from meeting, then start-up could occur sooner.
5/26/98 2MAPPS
v2.1 (south-capable) Subsystem Deliveries.
This is a best-case milestone, assuming no unexpected
challenges are found in southern data. This date will slip if major software
redesigns, or additional diagnostics and analysis are necessary to accommodate
southern data. Approximately 2.5 months of intensive southern data
analysis are budgeted to prepare for v2.1 if there are no new developments
required for the southern facility data. Note that 2MAPPS north and
south will be identical. All observatory and/or hemispheric specific differences
will be handled via parameter and name lists.
5/27-6/10/98 2MAPPS v2.1 System Integration and End-to-End Testing
The parallel pipeline is a platform where development
can take place independent of the operational pipeline to handle any newly
discovered software problems that compromise the ability to meet Level
1 Science Requirements, or to respond to major hardware emergencies,
such as the replacement of arrays in the survey cameras. The parallel
development pipeline will not be used as testbed for open-ended algorithm
design changes and testing.
Items currently under discussion for working in the parallel
development pipeline:
R. Cutri - IPAC
Last update 8/25/98