Camera Changes on 970122n
Date: Wed, 21 Jan 1998 21:19:31 -0500 (EST)
From: skrutski@north.phast.umass.edu (Mike Skrutskie)
Rae has made a number of changes on the mountain which, in
principle, should not affect the data, but people should
be on the lookout starting tonight (22 Jan UT).
He removed a resistor on one of the ADC boards. The
swaping of these boards was previously associated
with a 1 pixel jump in band-to-band pointing.
The removal of the resistor should have no effect, however...
Also, he exercised the gain and offset pots on the ADC boards.
These are minor trim adjustements and should only produce
tiny changes
in the system gain, probably at an undetectable level.
Date: Wed, 21 Jan 1998 23:44:33 +0000 (GMT)
From: Rae Stiening
Camera lower fiber box:
Added heat sinks to two Xilinx memory address decoders and
3.3v regulator.
Removed C124 to speed boot up.
Cleaned dust from box.
Removed U23 (seprom) #44 and replaced it with "TEST". This
seprom is not used in normal operations.
Wrapped up LFB-Raptor cables to reduce electrical pickup.
Camera SV21 card
SV21 Serial F35988 which was in service was replaced with
SV21 Serial F38103.
Operating system updated from Gatir 1.10 to 1.11.
J-Band ADC card (serial #2)
No changes.
Does not have paralleled gates.
Has pots. Pots were exercised to make sure contacts are clean.
H-Band ADC card (serial #6)
Removed 2k pull up resistor
Has parallel gates which were not changed.
Does not have posts
K-Band ADC card
No changes
Does not have paralleled gates.
Has pots. Pots were exercised to make sure contacts are clean.
Camera Upper Fiber Board
Screwed 3.3v regulator to board with thermal compound to
improve cooling.
Script (NI2MASS) software changes
Checked contents of NI2MASS/Current against floppy disk archive
"Hopkins archive 11/14/97"
No change for following files:
script.c,ctdir.c,tdir.c,script.ini,script.lst,mks.bat,purge,bat
chkpurge.bat,abort.txt,camboot.sct,camwake.sct,dark.sct,focus.sct,
newlog.sct,point.sct,preset.sct,shutdown.sct,start_up.sct, and
view.sct
The following files had a 499mS wait ahead of store_data_d removed
on 11/20/97: cal.sct,survey.sct,tst.sct, and view.sct.
It is correct to remove this 499mS wait because the changes to
the weather station routines in SCRIPT could not have been
related to this delay.
Checked to see that executable script.exe is binary identical to
a today compile from script.c. It was.
Software changes to Script.c today:
An explicit raptor command to disable raptor interrupts was added
to the initialization routines. Change is documented
in Script.dif attached to this e-mail.
Software change to Camboot.sct today:
A dummy serial command to clear any excess characters on bootup
was added.
A hard reset to the SV21 during bootup was added to the operator
instructions. Change is documented in Camboot.dif
attached to this e-mail.
TCS changes:
A logic error in the mirror cover open detection circuitry was
corrected. Until today when either mirror cover was open
TCS would report mirror covers open. After today BOTH
covers must be open before TCS will report covers open.
This change is not in the hardware loop which the cover
actuators use to detect full open.
The startup script will now hang on mirror covers open check if
both covers are not open. The operator will have to
investigate why the switchs are not closed before
proceeding.